Guidance of product, service Product
V2X system

With fast charging station for EV
We utilized battery facilities
Emergency power source system
Summary
This product is emergency power source system which by unifying fast charging station and battery facilities, enables long-time stable power supply for at the time of disaster. We play an active part as charge station and electricity peak cut system in normal. In addition, we can utilize electricity which generated electricity for own house consumption and securing of emergency power source if we add PV system.
Use
01.Emergency power source
- We can stably supply electricity to important load such as lighting or air-conditioner in building at the time of blackout using ability of EV for generation, accumulation of electricity and battery for emplacement
- If electricity of in-vehicle battery of EV is short, supplying power for long term is possible by spare operation of vehicle containing
- Power supply is possible to ministry of three load apparatus that large-capacity electricity including elevator is necessary
- At the time of return from blackout, is automatic without letting power supply cut off; available for reconnection in commercial school (during patent application)
02.Fast charging station
- We can use as up to five fast charging stations
- We reduce electricity peak at the time of EV charge and can reduce increase of electric base rate
03.Electricity peak cut system
-
We equalize electricity demand in building using battery and battery for emplacement which we put on EV and reduce electric bill
※B03 is bells and whistles.
Features
We automatically change power supply function
Station controller equipped with us's original autonomy distributed coordination control technology "Synergy Link" recognizes normal time and the situation in emergency, each function all; is automatic, and station controller equipped with realization us's original autonomy distributed coordination control technology "Synergy Link" by the most suitable operation that accepted change, the situation recognizes normal and the situation in emergency, is realization by all most suitable operation that is automatic, and accepted change, the situation by each function
※B03 is bells and whistles.
Juxtaposition of photovoltaic power generation is possible, too
Construction of system which considered equal environment only sunlight with charge electricity to EV if we add sunlight system is enabled and contributes to CO2 reduction
B01
We realize space-saving setting construction shortening
It is placeable in space for one parking lot, and setting is possible again in a minimum period of one day
B03
Compact design
Placement that is flexible with two cube shapes with high design is possible
A little at battery capacity
We make battery capacity small quantity and are most suitable for Small start
Specifications
Item | B01 | B03 | |
---|---|---|---|
Setting image |
![]() |
![]() |
|
Specifications |
System juhodendenryoku (maximum) |
50kW | |
The output voltage |
Ministry of three 6,600V |
Ministry of three 210V |
|
Frequency | 50/60 Hz | ||
Battery capacity | 50kWh | 14kWh | |
EV ju Discharger connection Possible number |
Five | ||
Setting Place The outskirts Environment |
Altitude | 1,000m above sea level or less | |
Use place | The outdoors | ||
Ambient temperature | -10 degrees Celsius - 40 degrees Celsius | ||
The neighborhood atmosphere |
Is flammable, is corrosive Liquid ・ Gas Do not exist |
||
Having damage from salt breeze or not | Nothing | ||
The snow |
1.0m The following |
0.6m The following |